Third Pump Station Construction Update: Weekend Construction Activity – Sunday, December 20, 2020

FBCLID 2 Third Pump Station
2602 Oakland Drive
Sugar Land, TX 77479

The last major concrete placement on the Third Pump Station Project will complete the deck where the new stormwater pumps are installed.  This critical activity is still scheduled for Wednesday, December 30.  However, recent wet weather has slowed down the crews preparing forms for the concrete placement.  The electrical crew installing the conduit in the pump deck is now scheduled to work on Sunday, December 20.  The contractor will not operate any equipment on site before 8:00 a.m.

On Wednesday, December 30, the pump deck concrete placement will require additional early morning work hours, and the contractor will arrive onsite by 2:00 a.m.  At 4:00 a.m. concrete trucks will start arriving and are expected to run continuously until 1:00 p.m.  The concrete finishing crews will be complete by 4:00 p.m. and evening work hours will not be required.  The contractor will stage concrete trucks on Elkins Road, in front of Clements High School, to limit parking on Oakland Drive inside the neighborhood.  Please remain aware of construction activity during this time.  A follow-up notification will be distributed the week prior when all dates and times are confirmed.

The Third Pump Station is still scheduled to be in operation by Spring 2021, before the start of Hurricane Season.  FBCLID 2 appreciates your patience, particularly the residents of Austin Meadows, as the District works to complete this critical flood control project.

Additional details are available at: www.fbclid2.com/third-pump-station-construction/.

Please contact FBCLID 2 directly with any questions or concerns: www.fbclid2.com/contact.

Third Pump Station Construction Update: Overnight Construction Activity – December 30, 2020

Flintco Industrial continues to make progress on construction of the Third Pump Station. The intake structure and outfall for the pump station are essentially complete. The foundation and walls for the pump bays are also complete. The last major concrete pour on the project is placement of the top deck that is suspended over the pump bays. This critical activity is currently scheduled for Wednesday, December 30. The top deck pour will require additional work hours, so the contractor will arrive onsite by 2:00 a.m. At 4:00 a.m. concrete trucks will start arriving and are expected to run continuously until 1:00 p.m. The concrete finishing crews will be complete by 4:00 p.m. and evening work hours will not be required. The contractor will stage concrete trucks on Elkins Road, in front of Clements High School, to limit parking on Oakland Drive inside the neighborhood. Please remain aware of construction activity during this time. A follow-up notification will be distributed the week prior when all dates and times are confirmed.

The Third Pump Station is still scheduled to be in operation by Spring 2021, before the start of Hurricane Season. FBCLID 2 appreciates your patience, particularly the residents of Austin Meadows, as the District works to complete this critical flood control project.

An updated time-lapse video and additional details are available at: www.fbclid2.com/third-pump-station-construction.

Please contact FBCLID 2 directly with any questions or concerns: www.fbclid2.com/contact.

City of Sugar Land – SH 6 Widening Project

Beginning the week of December 7, 2020, SH 6 Widening Project will require the First Colony Community Services Association (FCCSA) Soldiers Field lake (FBCLID 2 Ditch “F”) to be drawn down approximately 2-feet in order for the city’s waterline improvements to be completed. Once the improvements are completed, the lake will be refilled to the required elevation.

City staff is coordinating with FCCSA and FBCLID 2 to ensure there are no adverse impacts. The entire operation is anticipated to be completed on/before Saturday, December 12, 2020, by 5:00 P.M.

If you have any questions please feel free to contact Keisha Seals, Project Manager, in the Engineering Department at 281-275-2780. For more information on construction updates visit www.sugarlandtx.gov and sign up for notifications or visit its.sugarlandtx.gov for more information on Sugar Land travel time data.