Third Pump Station Construction Update: Overnight Construction Activity Delayed – Rescheduled for Tuesday, January, 5 2021

FBCLID 2 Third Pump Station
2602 Oakland Drive
Sugar Land, TX 77479

The pump deck concrete placement previously scheduled for Monday, January 4, will be postponed one day. The pour has been rescheduled for Tuesday, January 5 and will require early morning work hours. The contractor will arrive onsite by 2:00 a.m. At 4:00 a.m. concrete trucks will start arriving and are expected to run continuously until 1:00 p.m. The concrete finishing crews will be complete by 4:00 p.m. and evening work hours will not be required. The contractor will stage concrete trucks on Elkins Road, near the Oakland Drive intersection, to limit parking inside the neighborhood. Please remain aware of construction activity during this time.

Additional details are available at: www.fbclid2.com/third-pump-station-construction/.

Please contact FBCLID 2 directly with any questions or concerns: www.fbclid2.com/contact.