Third Pump Station Construction Update: Overnight Construction Activity Delayed – Rescheduled for Monday Janurary, 4 2021

FBCLID 2 Third Pump Station
2602 Oakland Drive
Sugar Land, TX 77479

The pump deck concrete placement previously scheduled for Wednesday, December 30 is being postponed due to inclement weather. The pour has been rescheduled for Monday, January 4 and will require additional early morning work hours. At 4:00 a.m. concrete trucks will start arriving and are expected to run continuously until 1:00 p.m. The concrete finishing crews will be complete by 4:00 p.m. and evening work hours will not be required. The contractor will stage concrete trucks on Elkins Road, in front of Clements High School, to limit parking on Oakland Drive inside the neighborhood. Please remain aware of construction activity during this time.

Additional details are available at: www.fbclid2.com/third-pump-station-construction/.