Third Pump Station Construction Update

Factory testing has started on the seven large pumps for the Third Pump Station.  The test for Pump #1 was successful, and it will be delivered to Sugar Land in early July.  FCBLID 2 has approved overtime and weekend work for the construction contractor to make Pump #1 operational as soon as possible.  Based on the latest schedule, the first pump will be operational by the end of August.  It will take approximately one month to complete the testing procedure for all seven pumps.  The current schedule estimates all new pumps will be in operation by the end of September.

FBCLID 2 appreciates your patience as the District works to complete this critical flood control project.  Additional details are available at: www.fbclid2.com/third-pump-station-construction/.  Please contact FBCLID 2 directly with any questions or concerns: www.fbclid2.com/contact.