Third Pump Station Construction Update – September 3, 2021

Third Pump Station Construction

Four pumps are now operational at the new FBCLID 2 pump station located at 2602 Oakland Drive in Sugar Land, behind Clements High School.  Four years ago, during Hurricane Harvey, the operation of these four new pumps would have prevented homes from flooding inside FBCLID 2.  When complete, the Third Pump Station will operate seven large storm water pumps that are powered by 1,500-horsepower motors. When combined, all seven pumps will move more than 1,000,000 gallons of water per minute, which represents a 400% increase in pumping capacity.

The final three pumps are scheduled to arrive at the new pump station the week of September 20.  After the final pumps arrive, it will still take 6-7 weeks to complete all pump installation in early November.  FBCLID 2 will soon bid a final contract that will put the finishing touches on the new pump station after the main constriction contract is complete.  The final site improvements include decorative fencing, landscaping, additional parking, and an operator’s office.  The District plans to host a public event for the community in late-2021 or early-2022, when all construction is complete.

FBCLID 2 appreciates your patience as the District works to complete this critical flood control project.  Please contact FBCLID 2 directly with any questions or concerns: www.fbclid2.com/contact.

New Pump Test (September 2, 2021)

Third Pump Station Construction Update – August 24, 2021

Third Pump Station Construction

Four of the seven pumps have arrived in Sugar Land for installation.  Based on the current schedule, the first will be ready to operate the week of August 30.  As soon as it is operational, this single pump will almost double the current pump capacity in Ditch A.  Two and potentially three additional pumps are also scheduled to be working by the end of next week.  The final three pumps are scheduled to arrive at the new pump station the week of September 20.  After the final pumps arrive, it will still take 6-7 weeks to complete all installation in early November.

FBCLID 2 appreciates your patience as the District works to complete this critical flood control project.  Additional details are available at: www.fbclid2.com/third-pump-station-construction/. Please contact FBCLID 2 directly with any questions or concerns: www.fbclid2.com/contact.

Ken DeMerchant (Fort Bend County Commissioner – Precinct 4) and Bryan Chapline (FBCLID 2 Board President) inspect the installation of Pumps 1-4.

Third Pump Station Construction Update: Weekend Construction Activity – Sunday, December 20, 2020

FBCLID 2 Third Pump Station
2602 Oakland Drive
Sugar Land, TX 77479

The last major concrete placement on the Third Pump Station Project will complete the deck where the new stormwater pumps are installed.  This critical activity is still scheduled for Wednesday, December 30.  However, recent wet weather has slowed down the crews preparing forms for the concrete placement.  The electrical crew installing the conduit in the pump deck is now scheduled to work on Sunday, December 20.  The contractor will not operate any equipment on site before 8:00 a.m.

On Wednesday, December 30, the pump deck concrete placement will require additional early morning work hours, and the contractor will arrive onsite by 2:00 a.m.  At 4:00 a.m. concrete trucks will start arriving and are expected to run continuously until 1:00 p.m.  The concrete finishing crews will be complete by 4:00 p.m. and evening work hours will not be required.  The contractor will stage concrete trucks on Elkins Road, in front of Clements High School, to limit parking on Oakland Drive inside the neighborhood.  Please remain aware of construction activity during this time.  A follow-up notification will be distributed the week prior when all dates and times are confirmed.

The Third Pump Station is still scheduled to be in operation by Spring 2021, before the start of Hurricane Season.  FBCLID 2 appreciates your patience, particularly the residents of Austin Meadows, as the District works to complete this critical flood control project.

Additional details are available at: www.fbclid2.com/third-pump-station-construction/.

Please contact FBCLID 2 directly with any questions or concerns: www.fbclid2.com/contact.